Line I · Law stated as of 10 November 2026

The insolvency and SARFAESI line. Two routes that begin with a demand notice.

An operational creditor may use the Insolvency and Bankruptcy Code, 2016. A secured creditor may use the SARFAESI Act, 2002. The two are separate routes and are drawn on separate tracks.

Only time limits set by law. Where the law sets none, the leg says “No fixed time in law”. Where the Act sets a target for the court rather than a deadline, the leg says so. The map does not estimate how long a court will take, and it says nothing about outcomes.

The insolvency and SARFAESI line (I) and its stationsIBC demand noticeApplication to the NCLTSARFAESI noticePossession and other measuresDRTDRAT
  • A step in the process
  • Interchange with another line
  • A court the route connects to
  • Dashed: no fixed time in law

Your station

Choose a station on the map to see what it is, the time the law sets to the next stop, and the source. Then press “I'm here” to light up the road ahead.

Settlement exits and links to courts are listed in each station's panel.

Every stop, in order

  1. IBC demand notice

    An operational creditor's demand notice under the Insolvency and Bankruptcy Code, which applies where the default is at least ₹1 crore. Source: IBC 2016, s. 4, as substituted by S.O. 1205(E), 24 March 2020.

    Where in Delhi

    No court at this step.

    • Next Application to the NCLT: 10 days. Ten days from receipt of a demand notice to bring a dispute or proof of payment to the creditor's notice. Source: IBC, s. 8(2).
    • Interchange Notice. Several routes begin with a notice. Each Act sets its own period: 15 days to pay a cheque, ten days under the IBC, sixty days under SARFAESI. Arbitration begins when the notice is received. Sources: NI Act, s. 138 proviso (c); IBC, s. 8(2); SARFAESI Act 2002, s. 13(2); Arbitration Act, s. 21. Connects with: Demand notice (Cheque bounce line, N); Legal notice (Recovery line, R); Notice under s. 21 (Arbitration line, A).
    • Interchange Recovery to IBC. Where the default is at least ₹1 crore, an operational creditor may send a demand notice under the IBC. Source: IBC 2016, s. 4, as substituted by S.O. 1205(E), 24 March 2020. Connects with: Legal notice (Recovery line, R).

    Read more: The IBC demand notice · IBC demand notice: the 10 days · Company in insolvency · Request a consultation

  2. Application to the NCLT

    After ten days without payment or notice of dispute, the operational creditor may apply to the Tribunal. The application is rejected where a notice of dispute was received. If it is admitted, a moratorium bars suits, proceedings and execution against the company. Sources: IBC, s. 9(1); IBC, section 9(5)(ii)(d); IBC s.14(1)(a), (3)(b).

    Where in Delhi

    • National Company Law Tribunal (NCLT). NCLT, Principal Bench and New Delhi Bench, Block 3, CGO Complex, Lodhi Road, New Delhi 110003. Both benches sit for the Union Territory of Delhi.

    The last stop on this route.

    Read more: IBC demand notice: the 10 days · Company in insolvency · Request a consultation

  3. SARFAESI notice

    A secured creditor's demand notice under section 13(2) of the SARFAESI Act. The borrower may make a representation, and the creditor gives its reasons within 15 days. Sources: SARFAESI Act 2002, s. 13(2); SARFAESI Act 2002, ss. 13(3A), 13(4), 13(13), 17(1), 18.

    Where in Delhi

    No court at this step.

    • Next Possession and other measures: 60 days. A SARFAESI demand notice gives sixty days from the date of the notice. Source: SARFAESI Act 2002, s. 13(2).

    Read more: The SARFAESI notice · SARFAESI notice: the next 60 days · SARFAESI notice received · Request a consultation

  4. Possession and other measures

    If the borrower does not pay within the 60 days, the creditor may take the measures in section 13(4), including possession. Source: SARFAESI Act 2002, ss. 13(3A), 13(4), 13(13), 17(1), 18.

    Where in Delhi

    The secured creditor. No court at this step.

    • Next DRT: 45 days. An application to the Debts Recovery Tribunal within 45 days. Source: SARFAESI Act 2002, ss. 13(3A), 13(4), 13(13), 17(1), 18.

    Read more: SARFAESI notice: the next 60 days · SARFAESI and DRT practice page · Request a consultation

  5. DRT Court

    The borrower's application against the measures, before the Debts Recovery Tribunal. Source: SARFAESI Act 2002, ss. 13(3A), 13(4), 13(13), 17(1), 18.

    Where in Delhi

    • Debts Recovery Tribunal (DRT). DRT-1, DRT-2 and DRT-3 Delhi, 4th Floor, Jeevan Tara Building, Parliament Street, New Delhi 110001. The three Delhi Tribunals sit in the same building.
    • Next DRAT: 30 days. An appeal to the Debts Recovery Appellate Tribunal within 30 days from the date the Tribunal's order is received. Source: SARFAESI Act 2002, s. 18(1).

    Read more: SARFAESI and DRT practice page · Request a consultation

  6. DRAT Court

    An appeal to the Debts Recovery Appellate Tribunal. It is not heard unless the borrower deposits 50% of the debt (as claimed by the creditor or as determined by the Debts Recovery Tribunal, whichever is less); the Appellate Tribunal may reduce this to not less than 25%, with reasons in writing. Sources: SARFAESI Act 2002, ss. 13(3A), 13(4), 13(13), 17(1), 18; SARFAESI Act 2002, s. 18(1), second and third provisos.

    Where in Delhi

    • Debts Recovery Appellate Tribunal (DRAT). DRAT Delhi, Apartment 318, 3rd Floor, Hotel Samrat, Kautilya Marg, Chanakyapuri, New Delhi 110021. The Appellate Tribunal for Delhi.

    The last stop on this route.

    Read more: SARFAESI and DRT practice page · Request a consultation

Read more

Urgent

If a hearing, deadline or limitation date is within the next 48 hours, call or WhatsApp +91 97170 52417 and say so at the start.

General information, not legal advice. Law stated as of 10 November 2026.

Reviewed by Ayush Ranjan, Advocate, on 19 November 2026.