Line A · Law stated as of 10 November 2026
The arbitration line. From the notice to the enforcement of the award.
Under the Arbitration and Conciliation Act, 1996, an arbitration begins with a notice and ends with an award, which can be challenged or enforced in court. The court can also be asked for interim relief.
Only time limits set by law. Where the law sets none, the leg says “No fixed time in law”. Where the Act sets a target for the court rather than a deadline, the leg says so. The map does not estimate how long a court will take, and it says nothing about outcomes.
- A step in the process
- Interchange with another line
- A court the route connects to
- Dashed: no fixed time in law
Your station
Choose a station on the map to see what it is, the time the law sets to the next stop, and the source. Then press “I'm here” to light up the road ahead.
Settlement exits and links to courts are listed in each station's panel.
A Arbitration line
Interim relief (s. 9)
A court can order interim measures before, during or after the arbitration, until the award is enforced. Source: Arbitration Act s.9(1) to (3).
Where in Delhi
- The “Court” under section 2(1)(e): the principal civil court of original jurisdiction, or the High Court in its ordinary original civil jurisdiction. The district court of the judicial district where a suit on the dispute would lie, in its district court complex (Tis Hazari (Central, West); Patiala House (New Delhi); Karkardooma (East, North-East, Shahdara); Rohini (North, North-West); Dwarka (South-West); Saket (South, South-East)), or the Delhi High Court, Sher Shah Road, New Delhi 110503 on its original side. The court that would have jurisdiction over the dispute if it were a suit (Arbitration Act, section 2(1)(e)).
Next stop
- Notice under s. 21: 90 days. After a court's interim order before arbitration, the arbitration must begin within 90 days or further time the court allows. Source: Arbitration Act, s. 9(2).
- Court Court: interim relief (s. 9). Interim measures from the court before, during or after the arbitration. Once the tribunal is constituted, the court will not take the application unless the remedy before the tribunal is not efficacious. Sources: Arbitration Act s.9(1) to (3); Arbitration Act, s. 9(2).
The road ahead
- Notice under s. 21 after Interim relief (s. 9): 90 days. After a court's interim order before arbitration, the arbitration must begin within 90 days or further time the court allows. Source: Arbitration Act, s. 9(2).
- Arbitrator appointed after Notice under s. 21: 30 days. 30 days to appoint or agree an arbitrator before the court can be asked to appoint. The Act asks the court to try to decide the application within 60 days of notice. Sources: Arbitration Act, s. 11(4), (5); Arbitration Act ss.10(2), 11(3) to (8), (12), (13).
- Pleadings complete after Arbitrator appointed: 6 months. Statement of claim and defence within six months of the arbitrators receiving notice of appointment. Source: Arbitration Act 1996, s. 23(4).
- Award after Pleadings complete: 12 + 6 months. Award within twelve months of completion of pleadings, extendable by consent by up to six months. Source: Arbitration Act, s. 29A(1), (3).
- Challenge (s. 34) after Award: 3 months + 30 days. Challenge within three months of receiving the award; 30 more days for sufficient cause, not after. Source: Arbitration Act, s. 34(3) and proviso.
- Enforcement (s. 36) after Challenge (s. 34): After s. 34 time. The award is enforced as a decree once the time for a section 34 challenge has run. A challenge does not stay it automatically; the court may stay it on conditions. The Act asks the court to try to decide the challenge within one year. Sources: Arbitration Act s.36(1) to (3); Arbitration Act ss.34(2), (2A), (3), (5), (6).
Other routes on the way
- Appeal (s. 37), from Challenge (s. 34): 60 days (₹3 lakh+). In a commercial dispute of specified value (₹3 lakh or more), 60 days for every appeal under section 37. Below that value, the Limitation Act applies: 90 days for an appeal from another court to a High Court, 30 days for an appeal within the High Court. A late appeal is allowed only by way of exception, not as a rule. Source: Commercial Courts Act 2015, s. 13(1A); Limitation Act, Schedule; Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460.
Connections ahead
- Interchange Notice. Several routes begin with a notice. Each Act sets its own period: 15 days to pay a cheque, ten days under the IBC, sixty days under SARFAESI. Arbitration begins when the notice is received. Sources: NI Act, s. 138 proviso (c); IBC, s. 8(2); SARFAESI Act 2002, s. 13(2); Arbitration Act, s. 21.
- Interchange Council's award to section 34. The Council's award is challenged under section 34, and a buyer must first deposit 75% as the court directs. Sources: MSMED Act and Delhi Council Rules, s. 18(3); r. 4(x); MSMED Act, s. 19 and proviso.
- Court Court: challenge (s. 34). The award can be challenged in court within three months of receiving it, with 30 more days for sufficient cause. Source: Arbitration Act, s. 34(3) and proviso.
Read more
A Arbitration line
Notice under s. 21
The arbitration begins on the date the respondent receives the request to refer the dispute. Source: Arbitration Act, s. 21.
Where in Delhi
No court at this step.
Next stop
- Arbitrator appointed: 30 days. 30 days to appoint or agree an arbitrator before the court can be asked to appoint. The Act asks the court to try to decide the application within 60 days of notice. Sources: Arbitration Act, s. 11(4), (5); Arbitration Act ss.10(2), 11(3) to (8), (12), (13).
- Interchange Notice. Several routes begin with a notice. Each Act sets its own period: 15 days to pay a cheque, ten days under the IBC, sixty days under SARFAESI. Arbitration begins when the notice is received. Sources: NI Act, s. 138 proviso (c); IBC, s. 8(2); SARFAESI Act 2002, s. 13(2); Arbitration Act, s. 21.
- Court Court: interim relief (s. 9). Interim measures from the court before, during or after the arbitration. Once the tribunal is constituted, the court will not take the application unless the remedy before the tribunal is not efficacious. Sources: Arbitration Act s.9(1) to (3); Arbitration Act, s. 9(2).
The road ahead
- Arbitrator appointed after Notice under s. 21: 30 days. 30 days to appoint or agree an arbitrator before the court can be asked to appoint. The Act asks the court to try to decide the application within 60 days of notice. Sources: Arbitration Act, s. 11(4), (5); Arbitration Act ss.10(2), 11(3) to (8), (12), (13).
- Pleadings complete after Arbitrator appointed: 6 months. Statement of claim and defence within six months of the arbitrators receiving notice of appointment. Source: Arbitration Act 1996, s. 23(4).
- Award after Pleadings complete: 12 + 6 months. Award within twelve months of completion of pleadings, extendable by consent by up to six months. Source: Arbitration Act, s. 29A(1), (3).
- Challenge (s. 34) after Award: 3 months + 30 days. Challenge within three months of receiving the award; 30 more days for sufficient cause, not after. Source: Arbitration Act, s. 34(3) and proviso.
- Enforcement (s. 36) after Challenge (s. 34): After s. 34 time. The award is enforced as a decree once the time for a section 34 challenge has run. A challenge does not stay it automatically; the court may stay it on conditions. The Act asks the court to try to decide the challenge within one year. Sources: Arbitration Act s.36(1) to (3); Arbitration Act ss.34(2), (2A), (3), (5), (6).
Other routes on the way
- Appeal (s. 37), from Challenge (s. 34): 60 days (₹3 lakh+). In a commercial dispute of specified value (₹3 lakh or more), 60 days for every appeal under section 37. Below that value, the Limitation Act applies: 90 days for an appeal from another court to a High Court, 30 days for an appeal within the High Court. A late appeal is allowed only by way of exception, not as a rule. Source: Commercial Courts Act 2015, s. 13(1A); Limitation Act, Schedule; Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460.
Connections ahead
- Interchange Council's award to section 34. The Council's award is challenged under section 34, and a buyer must first deposit 75% as the court directs. Sources: MSMED Act and Delhi Council Rules, s. 18(3); r. 4(x); MSMED Act, s. 19 and proviso.
- Court Court: challenge (s. 34). The award can be challenged in court within three months of receiving it, with 30 more days for sufficient cause. Source: Arbitration Act, s. 34(3) and proviso.
Read more
A Arbitration line
Arbitrator appointed
If the other side does not appoint or agree, the High Court can be asked to appoint (the Supreme Court in an international commercial arbitration). Source: Arbitration Act ss.10(2), 11(3) to (8), (12), (13).
Where in Delhi
- Delhi High Court. Delhi High Court, Sher Shah Road, New Delhi 110503. One High Court for the whole of Delhi.
- Supreme Court. Supreme Court of India, Tilak Marg, New Delhi 110001. One Supreme Court for India.
Next stop
- Pleadings complete: 6 months. Statement of claim and defence within six months of the arbitrators receiving notice of appointment. Source: Arbitration Act 1996, s. 23(4).
- Court Court: interim relief (s. 9). Interim measures from the court before, during or after the arbitration. Once the tribunal is constituted, the court will not take the application unless the remedy before the tribunal is not efficacious. Sources: Arbitration Act s.9(1) to (3); Arbitration Act, s. 9(2).
The road ahead
- Pleadings complete after Arbitrator appointed: 6 months. Statement of claim and defence within six months of the arbitrators receiving notice of appointment. Source: Arbitration Act 1996, s. 23(4).
- Award after Pleadings complete: 12 + 6 months. Award within twelve months of completion of pleadings, extendable by consent by up to six months. Source: Arbitration Act, s. 29A(1), (3).
- Challenge (s. 34) after Award: 3 months + 30 days. Challenge within three months of receiving the award; 30 more days for sufficient cause, not after. Source: Arbitration Act, s. 34(3) and proviso.
- Enforcement (s. 36) after Challenge (s. 34): After s. 34 time. The award is enforced as a decree once the time for a section 34 challenge has run. A challenge does not stay it automatically; the court may stay it on conditions. The Act asks the court to try to decide the challenge within one year. Sources: Arbitration Act s.36(1) to (3); Arbitration Act ss.34(2), (2A), (3), (5), (6).
Other routes on the way
- Appeal (s. 37), from Challenge (s. 34): 60 days (₹3 lakh+). In a commercial dispute of specified value (₹3 lakh or more), 60 days for every appeal under section 37. Below that value, the Limitation Act applies: 90 days for an appeal from another court to a High Court, 30 days for an appeal within the High Court. A late appeal is allowed only by way of exception, not as a rule. Source: Commercial Courts Act 2015, s. 13(1A); Limitation Act, Schedule; Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460.
Connections ahead
- Interchange Council's award to section 34. The Council's award is challenged under section 34, and a buyer must first deposit 75% as the court directs. Sources: MSMED Act and Delhi Council Rules, s. 18(3); r. 4(x); MSMED Act, s. 19 and proviso.
- Court Court: challenge (s. 34). The award can be challenged in court within three months of receiving it, with 30 more days for sufficient cause. Source: Arbitration Act, s. 34(3) and proviso.
Read more
A Arbitration line
Pleadings complete
The statement of claim and the defence are filed. Source: Arbitration Act 1996, s. 23(4).
Where in Delhi
- The arbitral tribunal.
Next stop
- Award: 12 + 6 months. Award within twelve months of completion of pleadings, extendable by consent by up to six months. Source: Arbitration Act, s. 29A(1), (3).
- Court Court: interim relief (s. 9). Interim measures from the court before, during or after the arbitration. Once the tribunal is constituted, the court will not take the application unless the remedy before the tribunal is not efficacious. Sources: Arbitration Act s.9(1) to (3); Arbitration Act, s. 9(2).
The road ahead
- Award after Pleadings complete: 12 + 6 months. Award within twelve months of completion of pleadings, extendable by consent by up to six months. Source: Arbitration Act, s. 29A(1), (3).
- Challenge (s. 34) after Award: 3 months + 30 days. Challenge within three months of receiving the award; 30 more days for sufficient cause, not after. Source: Arbitration Act, s. 34(3) and proviso.
- Enforcement (s. 36) after Challenge (s. 34): After s. 34 time. The award is enforced as a decree once the time for a section 34 challenge has run. A challenge does not stay it automatically; the court may stay it on conditions. The Act asks the court to try to decide the challenge within one year. Sources: Arbitration Act s.36(1) to (3); Arbitration Act ss.34(2), (2A), (3), (5), (6).
Other routes on the way
- Appeal (s. 37), from Challenge (s. 34): 60 days (₹3 lakh+). In a commercial dispute of specified value (₹3 lakh or more), 60 days for every appeal under section 37. Below that value, the Limitation Act applies: 90 days for an appeal from another court to a High Court, 30 days for an appeal within the High Court. A late appeal is allowed only by way of exception, not as a rule. Source: Commercial Courts Act 2015, s. 13(1A); Limitation Act, Schedule; Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460.
Connections ahead
- Interchange Council's award to section 34. The Council's award is challenged under section 34, and a buyer must first deposit 75% as the court directs. Sources: MSMED Act and Delhi Council Rules, s. 18(3); r. 4(x); MSMED Act, s. 19 and proviso.
- Court Court: challenge (s. 34). The award can be challenged in court within three months of receiving it, with 30 more days for sufficient cause. Source: Arbitration Act, s. 34(3) and proviso.
Read more
A Arbitration line
Award
The tribunal makes its award. An award is final and binding. Source: Arbitration Act s.35.
Where in Delhi
- The arbitral tribunal.
Next stop
- Challenge (s. 34): 3 months + 30 days. Challenge within three months of receiving the award; 30 more days for sufficient cause, not after. Source: Arbitration Act, s. 34(3) and proviso.
- Court Court: interim relief (s. 9). Interim measures from the court before, during or after the arbitration. Once the tribunal is constituted, the court will not take the application unless the remedy before the tribunal is not efficacious. Sources: Arbitration Act s.9(1) to (3); Arbitration Act, s. 9(2).
- Court Court: challenge (s. 34). The award can be challenged in court within three months of receiving it, with 30 more days for sufficient cause. Source: Arbitration Act, s. 34(3) and proviso.
The road ahead
- Challenge (s. 34) after Award: 3 months + 30 days. Challenge within three months of receiving the award; 30 more days for sufficient cause, not after. Source: Arbitration Act, s. 34(3) and proviso.
- Enforcement (s. 36) after Challenge (s. 34): After s. 34 time. The award is enforced as a decree once the time for a section 34 challenge has run. A challenge does not stay it automatically; the court may stay it on conditions. The Act asks the court to try to decide the challenge within one year. Sources: Arbitration Act s.36(1) to (3); Arbitration Act ss.34(2), (2A), (3), (5), (6).
Other routes on the way
- Appeal (s. 37), from Challenge (s. 34): 60 days (₹3 lakh+). In a commercial dispute of specified value (₹3 lakh or more), 60 days for every appeal under section 37. Below that value, the Limitation Act applies: 90 days for an appeal from another court to a High Court, 30 days for an appeal within the High Court. A late appeal is allowed only by way of exception, not as a rule. Source: Commercial Courts Act 2015, s. 13(1A); Limitation Act, Schedule; Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460.
Connections ahead
- Interchange Council's award to section 34. The Council's award is challenged under section 34, and a buyer must first deposit 75% as the court directs. Sources: MSMED Act and Delhi Council Rules, s. 18(3); r. 4(x); MSMED Act, s. 19 and proviso.
Read more
A Arbitration line
Challenge (s. 34)
An application to the court to set the award aside, on the grounds in section 34. Filing it does not by itself stay the award. Sources: Arbitration Act ss.34(2), (2A), (3), (5), (6); Arbitration Act s.36(1) to (3).
Where in Delhi
- The “Court” under section 2(1)(e): the principal civil court of original jurisdiction, or the High Court in its ordinary original civil jurisdiction. The district court of the judicial district where a suit on the dispute would lie, in its district court complex (Tis Hazari (Central, West); Patiala House (New Delhi); Karkardooma (East, North-East, Shahdara); Rohini (North, North-West); Dwarka (South-West); Saket (South, South-East)), or the Delhi High Court, Sher Shah Road, New Delhi 110503 on its original side. The court that would have jurisdiction over the dispute if it were a suit (Arbitration Act, section 2(1)(e)).
Next stops
- Enforcement (s. 36): After s. 34 time. The award is enforced as a decree once the time for a section 34 challenge has run. A challenge does not stay it automatically; the court may stay it on conditions. The Act asks the court to try to decide the challenge within one year. Sources: Arbitration Act s.36(1) to (3); Arbitration Act ss.34(2), (2A), (3), (5), (6).
- Appeal (s. 37) (a branch): 60 days (₹3 lakh+). In a commercial dispute of specified value (₹3 lakh or more), 60 days for every appeal under section 37. Below that value, the Limitation Act applies: 90 days for an appeal from another court to a High Court, 30 days for an appeal within the High Court. A late appeal is allowed only by way of exception, not as a rule. Source: Commercial Courts Act 2015, s. 13(1A); Limitation Act, Schedule; Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460.
- Interchange Council's award to section 34. The Council's award is challenged under section 34, and a buyer must first deposit 75% as the court directs. Sources: MSMED Act and Delhi Council Rules, s. 18(3); r. 4(x); MSMED Act, s. 19 and proviso.
- Court Court: challenge (s. 34). The award can be challenged in court within three months of receiving it, with 30 more days for sufficient cause. Source: Arbitration Act, s. 34(3) and proviso.
The road ahead
- Enforcement (s. 36) after Challenge (s. 34): After s. 34 time. The award is enforced as a decree once the time for a section 34 challenge has run. A challenge does not stay it automatically; the court may stay it on conditions. The Act asks the court to try to decide the challenge within one year. Sources: Arbitration Act s.36(1) to (3); Arbitration Act ss.34(2), (2A), (3), (5), (6).
Other routes on the way
- Appeal (s. 37), from Challenge (s. 34): 60 days (₹3 lakh+). In a commercial dispute of specified value (₹3 lakh or more), 60 days for every appeal under section 37. Below that value, the Limitation Act applies: 90 days for an appeal from another court to a High Court, 30 days for an appeal within the High Court. A late appeal is allowed only by way of exception, not as a rule. Source: Commercial Courts Act 2015, s. 13(1A); Limitation Act, Schedule; Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460.
Read more
A Arbitration line
Enforcement (s. 36)
The award is enforced in the same way as a decree of the court. Source: Arbitration Act, section 36(1).
Where in Delhi
- District commercial courts (₹3 lakh up to ₹2 crore). In the district court complex of the judicial district: Tis Hazari (Central, West); Patiala House (New Delhi); Karkardooma (East, North-East, Shahdara); Rohini (North, North-West); Dwarka (South-West); Saket (South, South-East). The district where the defendant lives, carries on business or works for gain, or where the cause of action arose, wholly or in part (Code of Civil Procedure, section 20).
- Delhi High Court, Commercial Division (above ₹2 crore). Delhi High Court, Sher Shah Road, New Delhi 110503. On its original side, for a commercial dispute above ₹2 crore.
In a commercial dispute (Commercial Courts Act, section 10, as the section 36 explainer gives it); an award can be enforced where it can be executed, for example where the assets are.
Next stop
This is the last stop on this line.
The road ahead
No further stops on this line.
Read more
A Arbitration line
Appeal (s. 37)
An appeal lies from an order under section 34. There is no second appeal. Source: Arbitration Act s.37.
Where in Delhi
- Commercial Appellate Division of the High Court, in a commercial dispute. Delhi High Court, Sher Shah Road, New Delhi 110503. Appeals in commercial disputes, from the district commercial courts and the Commercial Division.
- Delhi High Court. Delhi High Court, Sher Shah Road, New Delhi 110503. One High Court for the whole of Delhi.
The first in a commercial dispute; otherwise the High Court, which hears appeals from a District Judge exercising original jurisdiction.
Next stop
This is the last stop on this line.
The road ahead
No further stops on this line.
Read more
Every stop, in order
Notice under s. 21
The arbitration begins on the date the respondent receives the request to refer the dispute. Source: Arbitration Act, s. 21.
Where in Delhi
No court at this step.
- Next Arbitrator appointed: 30 days. 30 days to appoint or agree an arbitrator before the court can be asked to appoint. The Act asks the court to try to decide the application within 60 days of notice. Sources: Arbitration Act, s. 11(4), (5); Arbitration Act ss.10(2), 11(3) to (8), (12), (13).
- Interchange Notice. Several routes begin with a notice. Each Act sets its own period: 15 days to pay a cheque, ten days under the IBC, sixty days under SARFAESI. Arbitration begins when the notice is received. Sources: NI Act, s. 138 proviso (c); IBC, s. 8(2); SARFAESI Act 2002, s. 13(2); Arbitration Act, s. 21. Connects with: Demand notice (Cheque bounce line, N); Legal notice (Recovery line, R); IBC demand notice (Insolvency and SARFAESI line, I); SARFAESI notice (Insolvency and SARFAESI line, I).
- Court Court: interim relief (s. 9). Interim measures from the court before, during or after the arbitration. Once the tribunal is constituted, the court will not take the application unless the remedy before the tribunal is not efficacious. Sources: Arbitration Act s.9(1) to (3); Arbitration Act, s. 9(2).
Read more: Notice invoking arbitration received · Starting an arbitration · Arbitration timeline tool · Request a consultation
Arbitrator appointed
If the other side does not appoint or agree, the High Court can be asked to appoint (the Supreme Court in an international commercial arbitration). Source: Arbitration Act ss.10(2), 11(3) to (8), (12), (13).
Where in Delhi
- Delhi High Court. Delhi High Court, Sher Shah Road, New Delhi 110503. One High Court for the whole of Delhi.
- Supreme Court. Supreme Court of India, Tilak Marg, New Delhi 110001. One Supreme Court for India.
- Next Pleadings complete: 6 months. Statement of claim and defence within six months of the arbitrators receiving notice of appointment. Source: Arbitration Act 1996, s. 23(4).
- Court Court: interim relief (s. 9). Interim measures from the court before, during or after the arbitration. Once the tribunal is constituted, the court will not take the application unless the remedy before the tribunal is not efficacious. Sources: Arbitration Act s.9(1) to (3); Arbitration Act, s. 9(2).
Read more: Court appointment of an arbitrator (section 11) · Request a consultation
Pleadings complete
The statement of claim and the defence are filed. Source: Arbitration Act 1996, s. 23(4).
Where in Delhi
- The arbitral tribunal.
- Next Award: 12 + 6 months. Award within twelve months of completion of pleadings, extendable by consent by up to six months. Source: Arbitration Act, s. 29A(1), (3).
- Court Court: interim relief (s. 9). Interim measures from the court before, during or after the arbitration. Once the tribunal is constituted, the court will not take the application unless the remedy before the tribunal is not efficacious. Sources: Arbitration Act s.9(1) to (3); Arbitration Act, s. 9(2).
Read more: Arbitration timeline tool · Request a consultation
Award
The tribunal makes its award. An award is final and binding. Source: Arbitration Act s.35.
Where in Delhi
- The arbitral tribunal.
- Next Challenge (s. 34): 3 months + 30 days. Challenge within three months of receiving the award; 30 more days for sufficient cause, not after. Source: Arbitration Act, s. 34(3) and proviso.
- Court Court: interim relief (s. 9). Interim measures from the court before, during or after the arbitration. Once the tribunal is constituted, the court will not take the application unless the remedy before the tribunal is not efficacious. Sources: Arbitration Act s.9(1) to (3); Arbitration Act, s. 9(2).
- Court Court: challenge (s. 34). The award can be challenged in court within three months of receiving it, with 30 more days for sufficient cause. Source: Arbitration Act, s. 34(3) and proviso.
Read more: Challenging an award (section 34) · Enforcing an award (section 36) · Request a consultation
Challenge (s. 34) Court
An application to the court to set the award aside, on the grounds in section 34. Filing it does not by itself stay the award. Sources: Arbitration Act ss.34(2), (2A), (3), (5), (6); Arbitration Act s.36(1) to (3).
Where in Delhi
- The “Court” under section 2(1)(e): the principal civil court of original jurisdiction, or the High Court in its ordinary original civil jurisdiction. The district court of the judicial district where a suit on the dispute would lie, in its district court complex (Tis Hazari (Central, West); Patiala House (New Delhi); Karkardooma (East, North-East, Shahdara); Rohini (North, North-West); Dwarka (South-West); Saket (South, South-East)), or the Delhi High Court, Sher Shah Road, New Delhi 110503 on its original side. The court that would have jurisdiction over the dispute if it were a suit (Arbitration Act, section 2(1)(e)).
- Next Enforcement (s. 36): After s. 34 time. The award is enforced as a decree once the time for a section 34 challenge has run. A challenge does not stay it automatically; the court may stay it on conditions. The Act asks the court to try to decide the challenge within one year. Sources: Arbitration Act s.36(1) to (3); Arbitration Act ss.34(2), (2A), (3), (5), (6).
- Next Appeal (s. 37): 60 days (₹3 lakh+). In a commercial dispute of specified value (₹3 lakh or more), 60 days for every appeal under section 37. Below that value, the Limitation Act applies: 90 days for an appeal from another court to a High Court, 30 days for an appeal within the High Court. A late appeal is allowed only by way of exception, not as a rule. Source: Commercial Courts Act 2015, s. 13(1A); Limitation Act, Schedule; Government of Maharashtra v. Borse Brothers Engineers & Contractors Pvt. Ltd., (2021) 6 SCC 460.
- Interchange Council's award to section 34. The Council's award is challenged under section 34, and a buyer must first deposit 75% as the court directs. Sources: MSMED Act and Delhi Council Rules, s. 18(3); r. 4(x); MSMED Act, s. 19 and proviso. Connects with: Council's award (Recovery line, R).
- Court Court: challenge (s. 34). The award can be challenged in court within three months of receiving it, with 30 more days for sufficient cause. Source: Arbitration Act, s. 34(3) and proviso.
Read more: Challenging an award (section 34) · Request a consultation
Enforcement (s. 36)
The award is enforced in the same way as a decree of the court. Source: Arbitration Act, section 36(1).
Where in Delhi
- District commercial courts (₹3 lakh up to ₹2 crore). In the district court complex of the judicial district: Tis Hazari (Central, West); Patiala House (New Delhi); Karkardooma (East, North-East, Shahdara); Rohini (North, North-West); Dwarka (South-West); Saket (South, South-East). The district where the defendant lives, carries on business or works for gain, or where the cause of action arose, wholly or in part (Code of Civil Procedure, section 20).
- Delhi High Court, Commercial Division (above ₹2 crore). Delhi High Court, Sher Shah Road, New Delhi 110503. On its original side, for a commercial dispute above ₹2 crore.
In a commercial dispute (Commercial Courts Act, section 10, as the section 36 explainer gives it); an award can be enforced where it can be executed, for example where the assets are.
The last stop on this route.
Read more: Enforcing an award (section 36) · Request a consultation
Interim relief (s. 9) Branch Court
A court can order interim measures before, during or after the arbitration, until the award is enforced. Source: Arbitration Act s.9(1) to (3).
Where in Delhi
- The “Court” under section 2(1)(e): the principal civil court of original jurisdiction, or the High Court in its ordinary original civil jurisdiction. The district court of the judicial district where a suit on the dispute would lie, in its district court complex (Tis Hazari (Central, West); Patiala House (New Delhi); Karkardooma (East, North-East, Shahdara); Rohini (North, North-West); Dwarka (South-West); Saket (South, South-East)), or the Delhi High Court, Sher Shah Road, New Delhi 110503 on its original side. The court that would have jurisdiction over the dispute if it were a suit (Arbitration Act, section 2(1)(e)).
- Next Notice under s. 21: 90 days. After a court's interim order before arbitration, the arbitration must begin within 90 days or further time the court allows. Source: Arbitration Act, s. 9(2).
- Court Court: interim relief (s. 9). Interim measures from the court before, during or after the arbitration. Once the tribunal is constituted, the court will not take the application unless the remedy before the tribunal is not efficacious. Sources: Arbitration Act s.9(1) to (3); Arbitration Act, s. 9(2).
Read more: Interim relief in arbitration (section 9) · Request a consultation
Appeal (s. 37) Branch Court
An appeal lies from an order under section 34. There is no second appeal. Source: Arbitration Act s.37.
Where in Delhi
- Commercial Appellate Division of the High Court, in a commercial dispute. Delhi High Court, Sher Shah Road, New Delhi 110503. Appeals in commercial disputes, from the district commercial courts and the Commercial Division.
- Delhi High Court. Delhi High Court, Sher Shah Road, New Delhi 110503. One High Court for the whole of Delhi.
The first in a commercial dispute; otherwise the High Court, which hears appeals from a District Judge exercising original jurisdiction.
The last stop on this route.
Read more: Challenging an award (section 34) · Request a consultation
Read more
- Arbitration timeline tool
- Commercial arbitration practice page
- Challenging an award (section 34)
- Request a consultation
- All six lines
- Print the map as a poster