Explainer · INDIAN CONTRACT ACT, SS. 73, 74

Liquidated and delay damages: what sections 73 and 74 let a court award

Damages for breach of contract in India: section 73 losses, a sum named in the contract under section 74, penalties, delay clauses, and what must be proved.

  • Section 73Loss arising naturally from the breach, or known to be likely when the contract was made
  • Section 74Reasonable compensation, capped at the sum named in the contract

When a contract is broken, the party who suffers is entitled to compensation for the loss that naturally arose from the breach in the usual course of things, or that both parties knew, when they made the contract, was likely to result — but not for remote or indirect loss.1 If the contract itself names a sum payable on breach, the court awards reasonable compensation not exceeding that sum, whether the clause calls it liquidated damages or a penalty.1 The Supreme Court has held that loss or damage is still necessary, and that where actual loss can be proved, it must be proved.2

Section 73: ordinary damages

Section 73 of the Contract Act sets the measure of damages for breach.1

  • What is recoverable: compensation for loss or damage that naturally arose in the usual course of things from the breach, or that the parties knew, when they made the contract, to be likely to result from it.
  • What is not: remote and indirect loss.
  • Mitigation: in estimating the loss, the means that existed of remedying the inconvenience caused by the breach must be taken into account.

The section’s illustrations show how this works. Where goods are not delivered, the buyer recovers the difference between the contract price and the price at which like goods could have been bought when delivery was due (illustration (a)).1 A carrier told that a mill is stopped for want of a machine, and who delays it, pays the profit the mill would have made during the delay — but not the loss of a Government contract it was never told about (illustration (i)).1 A buyer who had resold at a higher price recovers by reference to the market price on the delivery date, not the lost resale profit (illustration (o)).1

Section 74: a sum named in the contract

Section 74 applies when a contract names a sum to be paid in case of breach, or contains any other stipulation by way of penalty. The party complaining of the breach is entitled, “whether or not actual damage or loss is proved to have been caused thereby”, to reasonable compensation not exceeding the amount so named or the penalty stipulated.1 A stipulation for increased interest from the date of default may itself be a penalty.1

The illustrations show the ceiling at work: where A promises to pay ₹1,000 if A fails to pay ₹500 on a given day, B recovers such compensation, not exceeding ₹1,000, as the court considers reasonable (illustration (a)).1

What the Supreme Court said in Kailash Nath

In Kailash Nath Associates v. DDA (2015) the Delhi Development Authority had forfeited a bidder’s earnest money and later re-auctioned the plot for much more. The Supreme Court held that there had been no breach by the bidder, and in any event no loss, and ordered the money refunded. It set out the law on section 74 in seven points:2

  1. Where a sum is named in the contract as liquidated damages, the party complaining of breach receives it as reasonable compensation only if it is a genuine pre-estimate of damages fixed by both parties and found to be such by the court. Otherwise, and where the sum is a penalty, only reasonable compensation is awarded, up to the sum named. The named sum is the upper limit.
  2. Reasonable compensation is fixed on the well-known principles of the law of contract, including those in section 73.
  3. Because section 74 awards compensation for damage or loss caused by a breach, damage or loss is a sine qua non for the section to apply.
  4. The section applies whether the party is plaintiff or defendant.
  5. The sum may already have been paid or be payable in future.
  6. The words “whether or not actual damage or loss is proved” mean that where it is possible to prove actual loss, proof is not dispensed with. Only where loss is difficult or impossible to prove can the named sum, if a genuine pre-estimate, be awarded.
  7. Section 74 applies to forfeiture of earnest money under a contract, but not to forfeiture under the terms of a public auction before an agreement is reached.

The Court added that compensation can only be given for loss suffered: “If damage or loss is not suffered, the law does not provide for a windfall.”2

Delay clauses

A delay or “liquidated damages” clause in a supply, construction or service contract is a sum named for breach, and so falls under section 74.1 Read with Kailash Nath, the questions a court asks are:2

  • Was there a breach — was the delay the defendant’s, and was time for performance fixed?
  • Was there loss or damage?
  • Can the actual loss be proved? If so, it must be.
  • If it cannot, is the named sum a genuine pre-estimate fixed by both parties?
  • In every case, the award is reasonable compensation, and never more than the sum named.

Whether a particular clause is a genuine pre-estimate depends on the contract and the facts; this page does not answer that for any clause.

Pleading damages and interest in a commercial suit

In a commercial suit the plaint must set out interest claimed in detail: whether the transaction is commercial, whether interest is claimed under the contract, an Act (named) or another basis, and the rate, the dates, the total and the daily rate after that date.3 A frivolous claim for damages can cost the plaintiff even when it wins the rest: the illustration to the amended section 35 of the Code is a plaintiff who obtains a money decree but whose damages claim is found frivolous and vexatious, and on whom the court may impose costs.3 See costs in a commercial suit.

Both sides

The party claiming The party answering
Ordinary damages (s. 73) Show the loss arose naturally, or was in both parties’ contemplation; show steps taken to limit it1 Argue remoteness, or that the loss could have been avoided1
A named sum (s. 74) Show breach and loss; prove actual loss where it can be proved2 Show no breach, no loss, or that actual loss is provable and smaller2
The ceiling The named sum is the most that can be awarded1, 2 The same: the court awards what is reasonable, up to it1, 2

Questions people ask

The contract says the sum is “not a penalty”. Does that settle it?

No. Section 74 applies to a sum named for breach “or any other stipulation by way of penalty”, and allows only reasonable compensation up to that sum.1 The label does not change the test.

Can we recover more than the sum in the clause?

Under section 74, no: the award may not exceed the amount named.1, 2

We have not suffered any loss. Can we still claim the clause amount?

The Supreme Court has held that loss or damage is a necessary condition for section 74.2

The commercial suits guide explains how a damages claim is brought. The contract clause glossary explains common clauses.

General information, not legal advice.

Sources

  1. Indian Contract Act, 1872, sections 73 and 74, with their illustrationsAct 9 of 1872Official source
  2. Kailash Nath Associates v. Delhi Development Authority, Supreme Court of India, 9 January 20152015 INSC 22; [2015] 1 S.C.R. 627; Civil Appeal No. 193 of 2015Official source
  3. Commercial Courts Act, 2015, the Schedule (Order VII rule 2A; section 35 of the Code as substituted)Act 4 of 2016, as amended by Act 28 of 2018Official source

General information, not legal advice. Law stated as of 22 November 2026; it may have changed since.