In short
When the other party breaks a contract, read the clauses on notice, cure, termination and disputes before taking any step, and give written notice of the breach. The party who suffers is entitled to compensation for the loss that naturally arose from the breach (Indian Contract Act, 1872, section 73). A suit for it must be filed within three years of the breach (Limitation Act, 1963, Schedule, Article 55).
The next 48 hours
- 1Find the contract and read the clauses on performance, notice and termination.
- 2List what was due, by when, and what has happened.
- 3Do not terminate the contract until the termination clause has been read.
The deadlines
- The notice and cure periods in the contract.
- A suit for compensation for breach of contract must be filed within three years of the breach (Limitation Act, 1963, Schedule, Article 55).
The routes
- A notice of breach. A written notice that sets out the breach and the period to cure it.
- Arbitration or a suit. Arbitration if the contract has a clause, or a commercial suit if not.
- Urgent protection. An application for a temporary injunction, where something must be preserved while the dispute runs (Code of Civil Procedure, 1908, Order XXXIX Rule 1), or to the court under Section 9 of the Arbitration and Conciliation Act where the contract has an arbitration clause.
How it usually runs
A party who suffers by a breach of contract is entitled to compensation for the loss that naturally arose from it, or that both sides knew was likely when they made the contract (Indian Contract Act, 1872, section 73). In some cases there is also a right to end the contract, or to have it performed.
Before any step, read the contract for four clauses: notice and cure, termination, limitation of liability, and dispute resolution. A termination that skips the contract's own procedure can itself be called a breach. If there is an arbitration clause the dispute goes to arbitration, though a court can still grant urgent interim protection.
What the law says
- Indian Contract Act, 1872, section 73
- A party who suffers by a breach of contract is entitled to compensation for the loss that naturally arose from it in the usual course of things, or that both parties knew was likely when they made the contract.
- Limitation Act, 1963, Schedule, Article 55
- A suit for compensation for breach of contract must be filed within three years of the breach.
- Commercial Courts Act, 2015, sections 2(1)(i) and 12A
- A commercial suit of ₹3 lakh or more that does not seek urgent interim relief cannot be filed until pre-institution mediation has been tried. The mediation is to finish in three months, extendable by two, and that time is left out of limitation.
- Code of Civil Procedure, 1908, Order XXXIX Rule 1
- A temporary injunction may be granted where property in dispute is in danger of being wasted, damaged or alienated, or where the defendant threatens to dispossess the plaintiff.
- Arbitration and Conciliation Act, 1996, section 9
- A court may grant interim protection before or during an arbitration. If it does so before the arbitration begins, the arbitration must start within 90 days.
What to avoid
- Terminating by email before the termination clause has been followed.
- Carrying on for months without recording your objection in writing.
- Withholding all payment when only part is disputed.
The papers to gather
What an advocate will ask first
- What exactly was promised, and what was not done?
- What do the notice, cure and termination clauses say?
- What is the loss so far, and how is it worked out?
- Is there an arbitration clause?