Consumer complaints: from the notice to the order and its execution, for the consumer and for the business- Case
- M/s. Imperia Structures Ltd. v. Anil Patni and Another
- Court
- Supreme Court of India, 2020
- Law
- Consumer Protection Act, 1986, sections 3 and 12(4); Real Estate (Regulation and Development) Act, 2016, sections 18, 71, 79, 88 and 89; Consumer Protection Act, 2019, section 100
- Citation
- [2020] 12 S.C.R. 373
- Neutral citation
- 2020 INSC 625
When a builder delays a flat, the buyer often has two possible forums: the Consumer Commission and the authority under the real estate law (RERA). Builders have argued that once RERA came in, only its authorities could hear the dispute. This judgment rejected that argument.
The case
Buyers booked apartments in a Gurugram project in 2011 and 2012 and signed builder buyer agreements in November 2013, with construction to be completed in 42 months. Years later the project was far from complete. In October 2017 the buyers filed consumer complaints before the National Commission, which found the builder deficient in service and ordered a refund of the amounts deposited with simple interest at 9% a year, and ₹50,000 costs to each complainant (paragraphs 2 to 11).
The builder appealed. It argued that the buyers were not consumers, and that once the RERA Act came into force on 1 May 2016, all questions about the project were for the RERA authorities alone. It also relied on the project’s registration under RERA, valid until 31 December 2020 (paragraph 15).
The Supreme Court (Uday Umesh Lalit and Vineet Saran, JJ.; judgment by Lalit, J.) dismissed the appeals.
What the Court decided
1. The facts were rightly found. The National Commission’s findings that the complainants were consumers and that the builder had delayed the construction were “absolutely correct” (paragraph 18).
2. Consumer remedies are additional. The Court has “consistently” held that the remedies under the consumer law are additional to other remedies, including those under special statutes, and that “the availability of an alternate remedy is no bar in entertaining a complaint” (paragraph 21).
3. RERA’s bar on civil courts does not reach the Commission. Section 79 of the RERA Act bars a civil court from entertaining matters the RERA authorities can decide. A Consumer Commission, though its proceedings are judicial, is not a civil court, so section 79 “does not in any way bar the Commission or Forum … to entertain any complaint” (paragraph 27).
4. The allottee chooses. Section 18 of the RERA Act gives its remedy “without prejudice to any other remedy available”, and section 88 says RERA is in addition to other laws. “Thus, the parliamentary intent is clear that a choice or discretion is given to the allottee whether he wishes to initiate appropriate proceedings under the CP Act or file an application under the RERA Act” (paragraph 28). The Court also quoted its earlier holding in Pioneer Urban Land that allottees’ remedies under the consumer law, RERA and the Insolvency Code are “concurrent remedies” (paragraph 31).
5. Registration under RERA does not postpone the claim. The promised period had expired long before the project was registered under RERA. The registration’s validity to 31 December 2020 did not defer the buyers’ right to sue: even under section 18 of RERA, “the period has to be reckoned in terms of the agreement and not the registration” (paragraph 33).
6. The 2019 Act keeps the position. Section 100 of the Consumer Protection Act, 2019, which says the Act is “in addition to and not in derogation of” any other law, is “akin to” section 3 of the 1986 Act, and was enacted after RERA came into force (paragraph 34).
What it did not decide
The Court did not decide what a homebuyer should choose between the forums, or what happens if the same claim is pursued in both. It decided that the Consumer Commission was not barred, and upheld the orders on these facts. The Court made a further award of ₹50,000 in costs in each case, over and above the amounts already ordered (paragraph 35).
Why it matters
For a homebuyer facing a delayed flat, the consumer route remains open alongside RERA, and the choice is the buyer’s, provided the buyer is a “consumer”. For a builder, a defence that “only RERA can hear this” does not succeed, and registration under RERA with a later completion date does not reset the date promised in the agreement.
The page on builder delay: RERA or the Commission and the consumer complaints guide explain the routes.
What to do now
Homebuyers. Keep the builder buyer agreement, the promised date and every payment receipt. Decide between the Commission and the RERA authority with the remedies of each in mind.
Builders. Answer on the agreement’s own dates and terms. The RERA registration period is not a defence to delay under the agreement.
Read the judgment
Read the court's own words before relying on this note.
Open the judgment (PDF, 38 pages)Copy from the Supreme Court Reports, [2020] 12 S.C.R. 373, as published by the Supreme Court's eSCR service (copy taken from the open-data mirror of the eSCR PDFs, CC BY 4.0)
On the court's websiteThe Supreme Court's judgment search. Search by judgment date: 2 November 2020 (Civil Appeal Nos. 3581-3590 of 2020)
- M/s. Imperia Structures Ltd. v. Anil Patni and Another, Supreme Court of India, 2 November 20202020 INSC 625; [2020] 12 S.C.R. 373; Civil Appeal Nos. 3581-3590 of 2020Official source
- Consumer Protection Act, 2019, section 100Act 35 of 2019Official source
Comments
Questions about the law are welcome. Comments cannot be answered as advice on a particular case, and a first comment is shown once it is approved.
No comments yet.
Please complete the check above and fill in every field.Thank you. Your comment will appear once it has been approved.Thank you. Your comment has been posted.Sorry, your comment could not be sent. Please try again.