Judgment note · Recovery

Patil Automation: pre-institution mediation is mandatory

Supreme Court, 2022: pre-institution mediation under Section 12A of the Commercial Courts Act is mandatory unless urgent interim relief is sought.

Case
Patil Automation Pvt. Ltd. v. Rakheja Engineers Pvt. Ltd.
Court
Supreme Court of India, 2022
Law
Section 12A, Commercial Courts Act, 2015
Citation
(2022) 10 SCC 1

Mediate first, or the suit can be rejected.

What the Court decided

  1. Pre-institution mediation under Section 12A is mandatory for a commercial suit, unless urgent interim relief is sought.

The Court declared Section 12A mandatory. A commercial suit filed without first trying pre-institution mediation is liable to have its plaint rejected under Order VII Rule 11 of the Code of Civil Procedure, unless the suit contemplates urgent interim relief. The declaration was made to operate prospectively, for suits filed on or after 20 August 2022.

Why it matters

Before this decision, High Courts had differed on whether the step could be skipped or cured later. After it, a plaintiff who goes straight to court without mediation, and without a real case for urgent relief, risks losing the suit at the threshold and having to start again, with limitation still running. Later decisions have read the exception narrowly: asking for interim relief is not enough if the plaint and documents do not show real urgency.

What to do now

  1. Check whether the claim is a commercial dispute of ₹3 lakh or more.
  2. Ask whether urgent interim relief is really needed. If it is, the plaint must show why.
  3. If it is not, apply for pre-institution mediation to the Legal Services Authority. The process is to finish within three months, extendable by two with consent, and that time is left out when limitation is counted (Commercial Courts Act, 2015, section 12A).
  4. Keep the non-starter report or failure report. It goes in with the plaint.
  1. Patil Automation v. Rakheja Engineers, Supreme Court of India, 2022(2022) 10 SCC 1; 17 August 2022Official source
  2. Section 12A, Commercial Courts Act, 2015Act 4 of 2016, s. 12AOfficial source

General information, not legal advice. Read the judgment itself before relying on this note.