- Section 32Force majeure under a term of the contract, express or implied (Energy Watchdog, para 32)
- Section 56Frustration outside the contract: the act becomes impossible or unlawful
- Cost is not enoughA rise in price, or a contract becoming onerous, does not frustrate it (Energy Watchdog, paras 35 to 40)
Force majeure and frustration both deal with an event, after a contract is made, that stops or seriously affects performance. They work differently. A force majeure clause is a term the parties agreed: the Supreme Court has said that where force majeure is relatable to an express or implied clause, it is governed by section 32 of the Indian Contract Act, 1872, and where an event occurs outside the contract, by the rule in section 56.1, 2 Frustration under section 56 ends the contract; a clause can do less, or more, depending on what it says. The leading modern decision is Energy Watchdog v. CERC (2017), where a sharp rise in the price of imported coal was held to be neither force majeure under the contract nor frustration.2
The short answer
- Two routes. Force majeure under a clause is governed by section 32 (contingent contracts). An event outside the contract is governed by section 56.2
- Section 56. A contract to do an act which, after it is made, becomes impossible, or by reason of an event the promisor could not prevent becomes unlawful, becomes void when the act becomes impossible or unlawful.1
- “Impossible” is not literal. Performance may be “impracticable and useless from the point of view of the object and purpose” of the parties, if an event “totally upsets the very foundation” of the agreement (Satyabrata Ghose, as summarised in Energy Watchdog).2
- Cost alone does not frustrate. “The performance of a contract is never discharged merely because it may become onerous to one of the parties”; a wholly abnormal rise in prices does not in itself get rid of the bargain.2
- The clause comes first. “When a contract contains a force majeure clause which on construction by the Court is held attracted to the facts of the case, Section 56 can have no application.”2
- After the contract ends. Whoever received an advantage under a contract that becomes void must restore it or make compensation for it (section 65).1
What the Act says
Section 32. Contingent contracts to do or not to do anything if an uncertain future event happens cannot be enforced by law unless and until that event has happened. If the event becomes impossible, such contracts become void.1 A force majeure clause is read through this section because it makes performance, or relief from performance, depend on whether a stated event happens.
Section 56 has three paragraphs:1
- An agreement to do an act impossible in itself is void.
- A contract to do an act which, after the contract is made, becomes impossible, or, by reason of some event which the promisor could not prevent, unlawful, becomes void when the act becomes impossible or unlawful.
- Where one person has promised to do something which he knew, or with reasonable diligence might have known, and which the promisee did not know, to be impossible or unlawful, he must make compensation to the promisee for any loss the promisee sustains through the non-performance.
The illustrations to section 56 include a contract to take in cargo at a foreign port, which becomes void when the promisor’s Government declares war against the country of the port (illustration (d)), and a contract to act at a theatre for six months, which becomes void on the occasions when the actor is too ill to act (illustration (e)).1
Section 65. When a contract becomes void, any person who has received any advantage under it is bound to restore it, or to make compensation for it, to the person from whom it was received.1 The illustration of a singer paid in advance who is too ill to sing shows the effect: the singer need not compensate for lost profit, but must refund the advance (illustration (d)).1
How the Supreme Court reads section 56
Energy Watchdog collected the Indian law on frustration before applying it.2
Satyabrata Ghose (1954). The second paragraph of section 56 is exhaustive of the law in India. The word “impossible” is not used in the sense of physical or literal impossibility. If “an untoward event or change of circumstance totally upsets the very foundation upon which the parties entered their agreement”, the promisor can be said to find it impossible to do the act. Where the contract itself contains a term under which performance would be discharged in certain circumstances, the dissolution takes place under the contract and is dealt with under section 32; frustration outside the contract is governed by section 56 (para 34).2
Alopi Parshad (1960). The Act does not enable a party to ignore the express covenants and claim payment at rates different from those stipulated on a vague plea of equity. A wholly abnormal rise or fall in prices is an unexpected obstacle that does not in itself get rid of the bargain. Only when the terms, read in the light of the circumstances when the contract was made, show that the parties never agreed to be bound in a fundamentally different situation does the contract cease to bind (para 35).2
Naihati Jute Mills (1968). A contract is not frustrated merely because the circumstances in which it was made are altered. The courts have no general power to absolve a party from performance because it has become onerous on account of an unforeseen turn of events (para 36).2
Narrow limits. The doctrine “must always be within narrow limits”. The Court relied on English decisions and texts for the same point: the closure of the Suez Canal did not frustrate a sale of groundnuts that could still be shipped the long way round at double the freight; a rise in cost or expense does not frustrate a contract; and a force majeure clause will not normally be construed to apply where the contract provides for an alternative mode of performance (paras 37, 38).2 It quoted the Sea Angel test: frustration needs “a break in identity between the contract as provided for and contemplated and its performance in the new circumstances”, and “mere incidence of expense or delay or onerousness is not sufficient” (para 39).2
Energy Watchdog: the facts and the decision
The facts. Power producers had bid to supply electricity to State utilities at tariffs they chose, some non-escalable, and signed long-term power purchase agreements. A change in Indonesian law in 2010 and 2011 aligned the export price of Indonesian coal to international market prices. The producers claimed relief on the grounds of force majeure and change in law.2
Frustration rejected. The fundamental basis of the agreements remained unaltered. “Nowhere do the PPAs state that coal is to be procured only from Indonesia at a particular price”; the price of coal was “entirely for the person who sets up the power plant to bear”. An unexpected rise in the price of coal “will not absolve the generating companies from performing their part of the contract for the very good reason that when they submitted their bids, this was a risk they knowingly took”. A non-escalable bid did not by itself bar a plea of frustration, but it showed that the risk of supplying at the tariff was on the producer (para 40).2
The clause read narrowly. The force majeure clause defined force majeure as an event or circumstance that “wholly or partly prevents or unavoidably delays” a party in performing, but only to the extent the event was not within its reasonable control and could not have been avoided with reasonable care. Its relief clause covered performance “prevented, hindered or delayed” (para 41).2 The Court accepted that the list of events was not exhaustive, but held:2
- “Force majeure clauses are to be narrowly construed.” The word “hindered” in the relief clause went with “partly prevents” in the definition, so there had to be something that at least partly prevented performance (para 43).
- A mere rise in price rendering a contract more expensive to perform does not constitute “hindrance” (para 43, relying on Tennants v. Wilson and Peter Dixon v. Henderson).
- The exclusions clause said force majeure did not include changes in the cost of fuel, or “the agreement becoming onerous to perform”. The clause itself made clear these were not force majeure events (para 44).
- Alternative modes of performance were available, “albeit at a higher price”. Neither the force majeure clause, “referable to Section 32”, nor section 56 applied (para 45).
Change in law. The Court held separately that the agreements’ change-in-law clause, read with its definition of “law”, referred only to Indian law, so the Indonesian change did not qualify; but a change in Indian coal policy in 2013 did, and the Central Commission was to decide the relief afresh (paras 48 to 54).2 A change-in-law clause is a different clause from force majeure, and its words decide its reach.
What a force majeure clause must decide, as points
This page does not give clause wording. Read with Energy Watchdog, a clause should decide:
| Question | What to decide | Why it matters |
|---|---|---|
| Which events count? | A list, and whether it is exhaustive | Lists are read with the definition; the Court accepted a non-exhaustive list but still read it narrowly (para 43) |
| What must the event do? | Prevent, delay, hinder, make more costly | “Hindered” was read with “partly prevents”; cost alone was not hindrance (para 43) |
| What is excluded? | Price changes, lack of funds, the party’s own default | The exclusions in Energy Watchdog decided the case (para 44) |
| Control and care | Outside reasonable control; not avoidable with reasonable care | Part of the definition the Court applied (para 41) |
| Notice | When and how the affected party must tell the other | Not discussed in the judgment; a matter for the clause |
| Relief | Suspension, extension of time, no breach, payment for capacity, termination after a period | The clause decides the relief; section 56 only makes the contract void |
| Termination | After how long a suspension either side may end the contract | Without a term, the contract continues unless section 56 applies |
| Money already paid | Refund, set-off, or retention for work done | If the contract becomes void, section 65 requires an advantage received to be restored or compensated |
| Change in law | Separately, and which country’s law | “Any law” was read as Indian law in Energy Watchdog (paras 48 to 52) |
How these clauses are fought over
The dispute. The party that cannot perform says an event within the clause, or a frustrating event, has excused it. The other side says the event is not within the clause’s words, that performance was only made costlier or slower, that alternative modes of performance existed, or that the risk was allocated by the contract. Where there is a clause, the first argument is about its words; section 56 is argued as an alternative, and Energy Watchdog holds that section 56 has no application where a force majeure clause is held attracted to the facts.2
The forum. Most commercial contracts with a force majeure clause also have an arbitration clause, so the tribunal decides first and the award may be challenged under section 34 of the Arbitration and Conciliation Act, 1996 (challenging an award). Without one, the dispute goes to the commercial court (which commercial court in Delhi). In Energy Watchdog itself the forum was a statutory regulator, the Central Electricity Regulatory Commission, with an appeal to the Appellate Tribunal for Electricity and then the Supreme Court.2 A party that needs to stop the other side acting on a disputed force majeure notice, for example by encashing a bank guarantee or terminating, may seek interim relief (section 9 relief; interim injunctions in commercial suits).
The judgment. Energy Watchdog is linked below. A judgment note on it is part of the stage’s later work.
Both sides
| Question | The party claiming relief | The party resisting |
|---|---|---|
| Is the event within the clause? | The event is listed, or falls in the general words | Clauses are read narrowly; the event is excluded or outside the words (paras 43, 44) |
| What did it do to performance? | It prevented or partly prevented performance | It only made performance costlier or slower (paras 35, 43) |
| Was there another way? | No alternative mode was available | Alternative modes were available, at a higher price (para 45) |
| Who bore the risk? | The parties did not contemplate this situation | The risk was knowingly taken, for example in a non-escalable bid (para 40) |
| Section 56 as an alternative | The foundation of the contract is gone | A clause attracted to the facts excludes section 56 (para 45) |
| Money | Restore what was received under the void contract (s. 65) | Account for work done and advantages received (s. 65) |
Common problems
- Relying on cost. A sharp price rise is the commonest reason given, and the one the Supreme Court has rejected most clearly.
- A clause with no exclusions. Without them, each side argues what the general words cover. With them, as in Energy Watchdog, the exclusions often decide the case.
- No notice provision, or a late notice. The judgment does not discuss notice; the clause and the correspondence do.
- Treating frustration as a suspension. Section 56 makes the contract void. If the parties want it paused and resumed, the clause must say so.
- Confusing force majeure with change in law. They are separate clauses with separate definitions.
What to bring to a first meeting
- The contract, its force majeure, change-in-law, termination and dispute clauses.
- A dated account of the event and its effect on each obligation.
- Every notice sent and received, with proof of delivery.
- What alternatives were considered, and what they would cost.
- Payments made and received, and work done to date.
Where an advocate comes in
Whether an event excuses performance is decided on the clause, the facts and the notices, often under time pressure. We advise on force majeure and frustration before notices go out, and act in the arbitrations and suits that follow. The contract clause glossary gives a plain meaning of force majeure; the drafting pages for commercial contracts list the documents it goes into. Termination after a long suspension is explained on ending a contract early.
The judgment relied on here: Energy Watchdog v. CERC, 2017 INSC 338 (PDF on legalup.in); the Supreme Court’s own copy can be found by its date (11 April 2017) at sci.gov.in.
General information, not legal advice.
Sources
- Indian Contract Act, 1872, sections 32, 56 and 65, with their illustrationsAct 9 of 1872Official source
- Energy Watchdog v. Central Electricity Regulatory Commission, Supreme Court of India, 11 April 20172017 INSC 338; [2017] 3 S.C.R. 153; Civil Appeal Nos. 5399-5400 of 2016Official source
Comments
Questions about the law are welcome. Comments cannot be answered as advice on a particular case, and a first comment is shown once it is approved.
No comments yet.
Please complete the check above and fill in every field.Thank you. Your comment will appear once it has been approved.Thank you. Your comment has been posted.Sorry, your comment could not be sent. Please try again.