In short
If a builder has not given possession by the date in the agreement, the buyer may withdraw and claim a refund with interest, or stay and claim interest for every month of delay (Real Estate (Regulation and Development) Act, 2016, section 18). The complaint goes to the Real Estate Regulatory Authority; a Consumer Commission is an alternative, within two years of the cause of action. If the builder is in insolvency, the buyer claims in that process as a financial creditor.
The next 48 hours
- 1Find the builder-buyer agreement and the promised possession date.
- 2Collect every payment receipt and the correspondence about delay.
- 3Check the builder's status: whether it is in insolvency.
The deadlines
- A consumer complaint is not admitted unless it is filed within two years from the cause of action, unless sufficient cause is shown.
The routes
- A Consumer Commission. A complaint for delay, refund or compensation. Which Commission depends on the value paid.
- The real-estate regulatory authority. A complaint to the Real Estate Regulatory Authority, for a refund with interest or for interest on the delay (Real Estate (Regulation and Development) Act, 2016, sections 18 and 31).
- The NCLT. Where the builder is in insolvency, the buyer files a claim as a financial creditor (Insolvency and Bankruptcy Code, 2016, section 5(8)(f), Explanation).
- Arbitration. Where the agreement has an arbitration clause.
How it usually runs
A homebuyer whose flat is late has more than one forum, and they overlap: the Real Estate Regulatory Authority, the Consumer Commission, arbitration if the agreement provides for it, and the insolvency tribunal if the builder is already there. They differ in what they can order.
The first decision is what you want: the flat, with interest for the delay, or your money back with interest. The Act gives a buyer that choice where possession is not given by the agreed date (Real Estate (Regulation and Development) Act, 2016, section 18). The second is the builder's condition. If insolvency has begun, the buyer files a claim in that process as a financial creditor.
What the law says
- Real Estate (Regulation and Development) Act, 2016, section 18(1)
- If the builder does not give possession by the date in the agreement for sale, a buyer may withdraw and claim a refund with interest and compensation, or stay and claim interest for every month of delay.
- Real Estate (Regulation and Development) Act, 2016, section 31(1)
- Any aggrieved person may complain to the Real Estate Regulatory Authority or its adjudicating officer for a contravention of the Act.
- Consumer Protection (Jurisdiction of the District Commission, the State Commission and the National Commission) Rules, 2021, rules 3 to 5
- The Commission is chosen by the amount paid: up to ₹50 lakh, the District Commission; above that and up to ₹2 crore, the State Commission; above ₹2 crore, the National Commission.
- Consumer Protection Act, 2019, section 69
- A complaint is not admitted unless it is filed within two years of the cause of action. A later complaint can be accepted for sufficient cause, with reasons recorded.
- Insolvency and Bankruptcy Code, 2016, section 5(8)(f), Explanation
- Money raised from a homebuyer under a real estate project is treated as a financial debt, so a buyer claims in the builder's insolvency as a financial creditor.
What to avoid
- Signing a possession letter or an undertaking that gives up the claim for delay.
- Stopping instalments without first putting the reason in writing.
- Choosing a forum on the strength of a group message, without reading your own agreement.
The papers to gather
What an advocate will ask first
- What is the date of the agreement, and the promised date of possession, including any grace period?
- How much of the price has been paid?
- Is the project registered under RERA, and has an occupancy certificate been issued?
- Do you want possession, or a refund?