In short
Section 15 fixes when a buyer must pay a supplier. If they agreed a date in writing, it is that date, and the agreed period can never exceed 45 days from acceptance or deemed acceptance. If nothing was agreed in writing, payment is due before the appointed day under section 2(b). Act 16 of 2026 did not amend section 15.
The text
The provision relied on MSMED Act, 2006, s. 15 78 words
Liability of buyer to make payment.
15. Where any supplier supplies any goods or renders any services to any buyer, the buyer shall make payment therefor on or before the date agreed upon between him and the supplier in writing or, where there is no agreement in this behalf, before the appointed day:
Provided that in no case the period agreed upon between the supplier and the buyer in writing shall exceed forty-five days from the day of acceptance or the day of deemed acceptance.
As in force on 19 November 2026 · Micro, Small and Medium Enterprises Development Act, 2006, section 15 · Act 27 of 2006, Gazette of India, Extraordinary, Part II, Section 1, No. 31, 16 June 2006 · Official copy
What it means
Two cases
Section 15 applies where any supplier supplies goods or renders services to any buyer. The date for payment depends on what was agreed in writing:
| Agreed in writing? | Payment is due |
|---|---|
| Yes | On or before the agreed date, and the agreed period can “in no case” exceed 45 days from the day of acceptance or deemed acceptance |
| No | Before the appointed day: the day after the fifteen days from acceptance or deemed acceptance end (section 2(b)) |
“In writing”
Only a written agreement fixes a date under section 15. A date agreed orally does not, and the buyer then has to pay before the appointed day.
The 45-day limit
The proviso says that in no case can the period agreed in writing exceed 45 days from the day of acceptance or the day of deemed acceptance. A contract that gives longer does not extend the time beyond 45 days.
Acceptance
The day of acceptance, and of deemed acceptance, comes from the Explanation to section 2(b). A written objection within fifteen days of delivery moves it to the day the supplier removes the objection. Each supply has its own day of acceptance, so a supply made in several deliveries has several due dates.
What follows a late payment
If the buyer does not pay as section 15 requires, section 16 makes it liable for compound interest, and section 17 makes it liable for the amount with that interest. Act 16 of 2026 did not amend section 15. It inserted section 15A after it, on how Central Public Sector Enterprises settle invoices.
Key figures
- 45 daysThe longest period a written agreement can give, from acceptance
- 15 daysFrom acceptance, where nothing was agreed in writing (with s. 2(b))
Related sections
- Section 14. Administration and utilisation of Fund or Funds.
- Section 15A. Mandatory settlement of receivables through Trade Receivables Discounting System.
- Section 2. Definitions.
- Section 16. Date from which and rate at which interest is payable.
- Section 17. Recovery of amount due.
- Section 18. Reference to Micro and Small Enterprises Facilitation Council.
- All sections of the MSMED Act
On LegalUp
- MSME delayed payments: the whole route, for suppliers and buyers
- The 45-day rule: when a buyer must pay a micro or small supplier
- MSME due-date calculator
- MSME interest calculator
- Buyer delaying an MSME supplier
Sources
- Micro, Small and Medium Enterprises Development Act, 2006, sections 2(b) and 15Act 27 of 2006, Gazette of India, Extraordinary, Part II, Section 1, 16 June 2006Official source
- Micro, Small and Medium Enterprises Development (Amendment) Act, 2026Act 16 of 2026, Gazette of India, Extraordinary, Part II, Section 1, 13 August 2026Official source